The company has invested $4 billion to start the internationally
first-class office building project in B35 Lujiazui. The World Financial
Center, which is graded as the third tallest building in Pudong, will
be completed in the early 2008. At the appointed time, the company will
move to the top floor of the building.
The World Financial Center, developed by the company, is located
at the nucleus zone in Lujiazui.
It occupies land of 9236 square meters. The construction site amounts
to 111038.39 square meters (84001.76 square meters for office building,
5934.03 square meters for business complete set). The construction height
reaches 269 meters. The World Financial Center faces the superior green
land in the south and is situated in the central area of bank street
zone, the Lujiazui Road and Yingcheng Central Road. It is a marked building
among the buildings in the north Lujiazui.
The World Financial Center is designed by Nikken Sekkei (Japan) Ltd.
which has established for more than 100 years. The exterior is broad
and elegant while the interior is square and utility. The design company
adopts cross passageway which skillfully plans the public space and
the structures for business properties. The 45-degree angle formed by
the buildings and Lujiazui central green constitutes a marked shape
with tall buildings in the north and low buildings in the south. In
the lobby, the wooden decorations portray a green and natural office
with trees growing from the green land to the interior. The combination
of nature and construction makes people feel that they are being in
the oasis of steel and cement forest.
The progress of the project:
- September 2002 Land Transfer Contract signed
- August 2004 Verification of expansion proposal passed, testing of
stakes finished
- September 2004 ¡¶Shanghai Construction Work (Underground Construction)
Proposal Permit Notice¡·¡¶License of Permit of Construction Work¡·and construction
commenced
- July 2005 Aquired¡¶License of Permit of Construction Work and Design¡·for
the aboveground part
- February 2006 Underground structure finished
- 25 June 2007 Construction of structure completed
- Completion date: Spring 2008
The construction team of the project:
- Design unit: Nikken Sekkei (Japan) Ltd.
- Associate design unit: Shanghai Institute of Architectural Design
& Research Co., Ltd.
- Electronical and mechanical design consultant: Parsons Brinckerhoff
Engineering and Technology (Beijing) Co., Ltd. Shanghai Branch
- Engineering and surveying consultant: Davis Langdon & Seah (Shanghai)
Construction Consultants Co., Ltd.
- Exterior design consultant: Meinhardt Exterior Engineering Design
(Hong Kong) Limited
- Lighting design consultant: Shanghai Citelum Lighting Design Co.,
Ltd.
- Supervision of engineering: Shanghai Hailong Engineer, Research and
Development Co., Ltd.
- Consultant of development in early stage: Savills Property Services
(Shanghai) Co., Ltd.
- Primary property management company: Jones Lang LaSalle Surveyors
(Shanghai) Co., Ltd.
- Leasing joint general agents: Jones Lang LaSalle Surveyors ( Shanghai)
Co., Ltd.,
CB Richard Ellis Property Services Co., Ltd.